Difference between revisions of "4DUSandEndoscope"
From NAMIC Wiki
Tag: 2017 source edit |
|||
| (4 intermediate revisions by one other user not shown) | |||
| Line 105: | Line 105: | ||
=== General To Do === | === General To Do === | ||
| − | {|border="0" | + | {|border="0" cellpadding="5" |
|- bgcolor="silver" | |- bgcolor="silver" | ||
| Line 149: | Line 149: | ||
* Responsible: Jan Gumprecht | * Responsible: Jan Gumprecht | ||
=== Details === | === Details === | ||
| + | * The module is available through svn: http://svn.na-mic.org/NAMICSandBox/trunk/IGTLoadableModules/4DUsEndoNav/ | ||
=== Progress === | === Progress === | ||
| Line 177: | Line 178: | ||
|height="10px" | | |height="10px" | | ||
| + | |||
| + | |- | ||
| + | |||
| + | | width="80px"| || colspan="2" width="550px"| Source Code checked in to svn ||align="center" width="50px" | x || width="120px" | Thu, Aug 6th | ||
|- | |- | ||
| Line 212: | Line 217: | ||
=== To Do === | === To Do === | ||
| − | {|border="0" | + | {|border="0" cellpadding="5" |
|- bgcolor="silver" | |- bgcolor="silver" | ||
| Line 228: | Line 233: | ||
|- | |- | ||
| − | | align="center" width="70px" | | + | | align="center" width="70px" bgcolor="#009900" | DONE || align="left" | Check in source to svn |
| + | |||
| + | |- | ||
| + | |||
| + | | align="center" width="70px" bgcolor="#009900" | DONE || align="left" | Include Second Window source code | ||
|- | |- | ||
| − | | align="center" width="70px" | DONE || align="left"| Create first prototyp of module, i.e. adapt IGTWizard Module | + | | align="center" width="70px" bgcolor="#009900" | DONE || align="left"| Create first prototyp of module, i.e. adapt IGTWizard Module |
|- | |- | ||
| Line 322: | Line 331: | ||
=== To Do === | === To Do === | ||
| − | {|border="0" | + | {|border="0" cellpadding="5" |
|- bgcolor="silver" | |- bgcolor="silver" | ||
| Line 422: | Line 431: | ||
=== To Do === | === To Do === | ||
| − | {|border="0" | + | {|border="0" cellpadding="5" |
|- bgcolor="silver" | |- bgcolor="silver" | ||
| Line 521: | Line 530: | ||
=== To Do === | === To Do === | ||
| − | {|border="0" | + | {|border="0" cellpadding="5" |
|- bgcolor="silver" | |- bgcolor="silver" | ||
| Line 610: | Line 619: | ||
=== To Do === | === To Do === | ||
| − | {|border="0" | + | {|border="0" cellpadding="5" |
|- bgcolor="silver" | |- bgcolor="silver" | ||
Latest revision as of 05:23, 11 April 2023
Home < 4DUSandEndoscopeContents
Project Page for 4D Ultrasound with Endoscopic Overlay
Collaborators
Jan Gumprecht
- E-Mail: jgumprec(at)bwh.harvard.edu
- Location: Kyushu, Japan
- Timezone: GMT + 9
Jae-Sung Hung, PhD
- E-Mail: hong(at)dem.med.kyushu-u.ac.jp
- Location: Kyushu, Japan
- Timezone: GMT + 9
Nobuhiko Hata, PhD
- E-Mail: hata(at)bwh.harvard.edu
- Location: Boston, USA
- Timezone: GMT - 5
Haiying Liu
- E-Mail: hliu(at)bwh.harvard.edu
- Location: Boston, USA
- Timezone: GMT - 5
Yamada Atsushi, PhD
- E-Mail: yamada.atsushi(at)nitech.ac.jp
- Location: Nagoya, Japan
- Timezone: GMT + 9
Project Description
The goal of this project is to create a new 3D Slicer Module that can overlay patient registered 4D US volumes with endoscopic images.
The Project is divided into four part: 4D Ultrasound Volume Reconstruction, Patient-Image Registration, Endoscope Overlay, and Endoscope Calibration. All four parts will be accessable through a single 3D Slicer Module.
Overall Progress
| Month | Week # | Start Date - End Date | Done | Date Done |
|---|---|---|---|---|
| Week 34 | 17.08 - 23.08 | |||
| Week 33 | 10.08 - 16.08 | |||
| Endoscopic Overlay and Endoscopic Calibration shall be finished | ||||
| August | Week 32 | 03.08.09 - 09.08.09 | ||
| New PC set up | x | Thu Jul, 30th | ||
| New PC arrived | x | Tue Jul, 28th | ||
| Week 31 | 27.07 - 02.08 | |||
| Project Page created | x | Fri Jul, 24th | ||
| July | Week 30 | 20.07.09 - 26.07.09 | ||
General To Do
| Tasks | |
|---|---|
| O | Fill Project Page with Information |
| O | Order new Frame Grabber Card |
| DONE | Set Up New Computer |
| DONE | Order new PC |
| DONE | Create Project Page |
Details
- The following frame grabber card only provides grayscale images: I-O DATA GV-VCP3R/PCI (video decoder chip CX2388x) [1]
3D Slicer Module
- Responsible: Jan Gumprecht
Details
- The module is available through svn: http://svn.na-mic.org/NAMICSandBox/trunk/IGTLoadableModules/4DUsEndoNav/
Progress
| Month | Week # | Start Date - End Date | Done | Date Done |
|---|---|---|---|---|
| Week 34 | 17.08 - 23.08 | |||
| Week 33 | 10.08 - 16.08 | |||
| Source Code checked in to svn | x | Thu, Aug 6th | ||
| Second Window works | x | Thu, Aug 6th | ||
| August | Week 32 | 03.08.09 - 09.08.09 | ||
| Created First prototype of module | x | Fri, Jul 31st | ||
| Week 31 | 27.07 - 02.08 | |||
| July | Week 30 | 20.07.09 - 26.07.09 | ||
To Do
| Tasks | |
|---|---|
| O | Close Second window with OS native commands, i.e. click the "X" in the right upper corner |
| O | Comprehend Prostate nav module's source code |
| DONE | Check in source to svn |
| DONE | Include Second Window source code |
| DONE | Create first prototyp of module, i.e. adapt IGTWizard Module |
4D Ultrasound Volume Reconstruction
- Responsible: Jan Gumprecht
Details
The project is described here: [[2]]
Progress
| Month | Week # | Start Date - End Date | Done | Date Done |
|---|---|---|---|---|
| Week 34 | 17.08 - 23.08 | |||
| Week 33 | 10.08 - 16.08 | |||
| August | Week 32 | 03.08.09 - 09.08.09 | ||
| Update Calibration and Spacing Handeling | ||||
| New Commandline parameter added to grab a test image | x | Tue, Jul 30th | ||
| All parameters of the calibration file are now used | x | Tue, Jul 28th | ||
| OpenIGTLink is now externally, no local copy within the source code is used anymore | x | Mon, Jul 27th | ||
| Week 31 | 27.07 - 02.08 | |||
| Show demo of the system | ||||
| July | Week 30 | 20.07.09 - 26.07.09 | ||
To Do
| Tasks | |
|---|---|
| O | Find Segmentation Fault |
| O | Update Handling of Spacing |
| O | Update Calibration Part |
| DONE | Set up existing Hardware for first demo |
| DONE | Update CalibrationFileReader |
Patient-Image Registration
- Responsible: Jae-Sung Hong
Details
Progress
| Month | Week # | Start Date - End Date | Done | Date Done |
|---|---|---|---|---|
| Week 34 | 17.08 - 23.08 | |||
| Week 33 | 10.08 - 16.08 | |||
| August | Week 32 | 03.08.09 - 09.08.09 | ||
| Start integration with 4D Ultrasound | ||||
| Week 31 | 27.07 - 02.08 | |||
|
| ||||
| July | Week 30 | 20.07.09 - 26.07.09 | ||
To Do
| Tasks | |
|---|---|
| O | Dummy Task |
Endoscope Overlay
- Responsible: Yamada Atsushi, Haiying Liu
Details
- OpenCV Module in Slicer3
- Multiple Camera Support in Slicer3
- Transrectal/Transperineal biopsy robot module merge
- Open CV Wiki
- Summer Second Display Project (Japanese)
Bug Fixes for the 3D Slicer Module
- There is a bug in OpenCV related to V4L2 devices:
Progress
| Month | Week # | Start Date - End Date | Done | Date Done |
|---|---|---|---|---|
| Week 34 | 17.08 - 23.08 | |||
| Week 33 | 10.08 - 16.08 | |||
| Endoscopic Overlay shall be finished | ||||
| August | Week 32 | 03.08.09 - 09.08.09 | ||
| Week 31 | 27.07 - 02.08 | |||
| July | Week 30 | 20.07.09 - 26.07.09 | ||
To Do
| Tasks | |
|---|---|
| O | Dummy Task |
| Endoscope overlay | |
Endoscope Calibration
- Responsible: Dr. Yang
Details
Progress
| Month | Week # | Start Date - End Date | Done | Date Done |
|---|---|---|---|---|
| Week 34 | 17.08 - 23.08 | |||
| Week 33 | 10.08 - 16.08 | |||
| Endoscopic Calibration shall be finished | ||||
| August | Week 32 | 03.08.09 - 09.08.09 | ||
| Week 31 | 27.07 - 02.08 | |||
| July | Week 30 | 20.07.09 - 26.07.09 | ||
To Do
| Tasks | |
|---|---|
| O | Dummy Task |